Chashma Nuclear Power Plant Units 3 & 4 (CHASNUPP-III and IV)

power

Cost

$2.4b
$2,370,000,000

operational

2017

Capacity

1k
MW Electricity

Description

The project constructed the third and forth reactors at the Chashma nuclear complex. These were negotiated together as a single package between the Chinese and Pakistanian governments in 2009–2010.

Finance

logo
$1.6b loan
Exim Bank of China
Development bank
$0.8b investment
Pakistan Government
Government